
A Petitioned Repair is any drainage system repair instigated by a petition. That petition can be generated by “an individual or an entity interested in or affected by a drainage system”. (Minn. Stat. § 103E.715) It can include “resloping ditches, incorporating multistage ditch cross-section, leveling spoil banks, installing erosion control, or removing trees” along with other repair activities.
When a drainage authority receives a Petition for Repair and determines that the drainage system needs repair, it shall appoint an engineer. In this case the engineer is required to examine the drainage system to determine the extent of the repair required including determination of the original grade or depth of the ditch (See Section B).
Recommended System Examination:
If the engineer appointed in relation to a petitioned repair finds that bridges and/or culverts in the drainage system provide inadequate hydraulic capacity for the efficient operation of the drainage system to serve its original purpose, the engineer shall make a hydraulic capacity report to the drainage authority. The hydraulic capacity report must include plans and specifications for the recommended replacement of bridges and culverts, the necessary details to make and award a contract, and the estimated cost.” (Minn. Stat. § 103E.721)
Upon completing the survey, the engineer must make a written report to the drainage authority. Drainage Law requires that the engineer's repair report document:
Following is a suggested outline for the repair report.
Although the scope of the engineer's Repair report is limited (relative to an engineer’s report required for a Drainage Project (see Section 3)), it still must contain sufficient information to be useful as a decision making tool for the drainage authority, and it must be presented at a hearing on the proceeding, as required by law (Minn. Stat. § 103E.715, Subds. 2, 3, and 4).
The content of the engineer's Repair report is, therefore, left up to the judgment of the engineer. Because of the nature of a Repair project, hydrologic and hydraulic design is not required by statute (as the original design has already been established). However, the engineer may determine that modeling or other design efforts may be necessary to meet the requirements of the DNR and/or USACOE, or determine the original drainage capacity.
Generally, there is no requirement for the engineer's Repair report to be reviewed by the commissioner of the DNR or the commissioner's staff. However, Minn. Stat. § 103E.701, Subd. 2 requires the drainage authority to notify the commissioner if the repair would affect public waters. At that point, the DNR may become involved in the proceeding if there is a dispute over the original "as constructed condition" if public waters may be affected). (See Section B)
Examples of repair reports can be found in Appendix 14.
Note: It is recommended that the engineer consider coordinating with DNR personnel early in the Repair proceeding, even if it appears unlikely DNR will become involved.
This page was last edited on 27 October 2016, at 16:33.
Template:Footer