
Ordinarily, the engineer prepares the construction contract; however, the drainage code contemplates that the drainage authority’s attorney, the engineer, and the attorney for the petitioners must prepare the contract and bond.762
The contract adopts the plans and specifications as prepared by the engineer.763 The plans and specifications section should provide that the engineer has the right, with the consent of the drainage authority, to modify the plans and specifications as work progresses and as circumstances require and that the contractor is obligated to provide it at the same rate stated in its bid.764
The contract should also include special terms that cover the following:
The contract and bond must include all provisions discussed in this chapter of the manual, in addition to the provisions found in Minn. Stat. § 574.26 to 574.32, and the Public Contractors’ Performance and Payment Bond Act.” The act requires the two bonds:
The penalty of performance bond and the payment bond must not be less than the contract price.770 If the contract price increases after the bond is given, the drainage authority may require additional bonds, the penalties of which must not be less than the amount of the increase in the contract price.771 The work under the contract shall cease if the bonds demanded are not furnished within ten days.772
The Public Contractors’ Performance and Payment Bond Act allows for reasonable attorneys’ fees, costs, and disbursements to be awarded in an action to enforce claims under the act.773
There is no statutory limit on how much time the contractor has to enter into a contract. In addition, if any portion of the work is to be done by the United States or an agency of the United States, a bond or contract is not necessary for that work unless required by laws governing the United States or its agencies.774
If a change increases the cost of the project, the engineer must bear in mind that the damages and costs’ of the project may not exceed the benefits found by the drainage authority.775 No change may be made if it will substantially impair the usefulness of any part of the project or system or substantially alter its original character.776
No changes to the original contract may be made that will cause any detrimental effects to the public interest under the environmental, land use, and multipurpose water management criteria in section 103E.015, subdivision 1.777
As a practical matter, minor changes are made by the engineer without a hearing.
If the drainage authority receives a request for a guarantee of tile work from a majority of the persons affected by the part of any project which is made up of drain tile, that part of the construction contract must be let separately.778 Such a request must be made before advertising for the letting of the work has begun.779 If the tile work is let separately, the contractor must guarantee the tile work installed pursuant to the contract for three years after its completion against any fault or negligence on the part of the contractor.780 The invitation to bid must make it clear that such a guarantee is required.781 The contractor’s performance bond in such case must contain a special provision guaranteeing the tile work.782
It is noteworthy that the statute requires the contractor only to guarantee the work against any fault or negligence on the part of the contractor. What if the material (the tile itself) fails?783 The contractor’s guarantee does not cover that. The drainage authority might have a cause of action against the manufacturer for breach of warranty, express or implied. Such an action could be brought for unreasonable failure of the product, even after three years had expired.
If a contractor fails to perform the contract according to specifications, the auditor or secretary should mail a notice of the default to the contractor, to the surety on the performance bond, to the engineer, and to the auditors of all affected counties.784 The notice should specify the default and state that, if the default is not promptly cured and the contract completed, the unfinished portion of the contract will be awarded to another contractor.785
The surety, on receiving such a notice, can be expected to respond. The surety will first contact the contractor to try to determine whether the contractor can or will perform. Often the problem ends there. If the contractor has become insolvent, bankrupt, or otherwise unable to complete the contract, the surety may hire a contractor of its own to complete the job. The auditors or secretary may grant an extension of time to accommodate the surety without convening the drainage authority.786 If the contract is completed by the surety, the balance owing on the contract should be paid to the surety, less damages incurred by the affected counties from the default.787
Damages incurred may be a matter of dispute. As always, it is difficult for the drainage authority to show damage. It is the landowners who are damaged, but the landowners do not get a chance to make a claim on the bond. The drainage authority cannot make a claim on behalf of the landowners. The only damages likely to be suffered by the drainage authority may come in the form of extra legal and engineering fees.
If the surety does not undertake to complete the contract or, having undertaken to do so, does not complete it within the specified time or extended time, the auditors of the affected counties or the secretary for a watershed district project may advertise for bids to complete the contract in the manner provided in the original letting.788 The drainage authority may recover any increased costs in completing the project from the original contractor’s bonding company.789 Such increased costs are not only the administrative costs involved in re-letting (publication, extra engineering, and legal), but also any construction costs in excess of the original contract.790
Part of the job of the project engineer is to inspect the work as it is being completed and to demand that it be done in accordance with the plan, specifications, and contract for construction.791 The project engineer is to submit a monthly report to the drainage authority showing the work completed since the previous report and all materials furnished under the contract.792
The contractor does not get paid until the engineer certifies a preliminary certificate for “work done and approved or for materials delivered.”793 The engineer’s certificate must show the station numbers covered by the certificate and state the value of the work done and the materials furnished according to the contract.794
Each preliminary certificate should show the volume in cubic yards of the excavation completed and must show that a loss will not occur if partial payment is made.795 For joint county drainage systems, the certificate must also show the total value to be paid by each county in the proportion fixed by the drainage authority order.796 A duplicate of the engineer's preliminary certificate is delivered to the auditor of each affected county or to the secretary of a watershed district.797
The affected counties or watershed district must then pay the contractor (based upon the certificate) 90 percent of the total value of the work done and approved and 90 percent of the total value of the material furnished and delivered.798 The contractor is not to cause materials to be delivered until they are needed and until delivery is authorized by the engineer.799
The contractor may, on a single contract exceeding $50,000, file a verified petition with the auditor requesting an order be made to pay 40 percent of the retained value of work and material if the following statements are true and made in the petition:
When a verified petition is filed, the auditor or secretary shall set a time and location for a hearing on the petition before the drainage authority and provide at least five days’ notice, by mail, of the hearing to the engineer, the attorney for the petitioners, the surety of the contractor’s bond, and auditors of the affected counties.801
A sample notice of hearing on petition for partial payment of retained contract amounts is found in Template E .
The drainage authority has the discretion of whether the grant the petition, but may only do so if it finds the following:
A template findings and order granting contractor’s petition for partial payment of retained contract amounts is found in Template F .
The auditors or secretary may, without convening the drainage authority, extend the time for the performance of a construction contract upon the contractor’s written application.803 Notice of the application for extension must be given to the project engineer, to the attorney for the petitioners, and to the auditors of the affected counties in the case of a joint county drainage project, but the decision is within the discretion of the auditor or watershed district secretary.804 The auditor(s) or secretary may grant an extension if sufficient reasons are shown.805 The granting of an extension does not necessarily mean that no liquidated damages may be sought.806 If the time for completing the contract expired before the extension was granted, there may still be liquidated damages sought and collected.807 If the extension expires, liquidated damages may again be sought.808
When a project takes more than one season to complete, the contractor may, after the first year’s work is completed and accepted by the engineer, apply for a reduction in the amount of the performance bond in order to reduce the renewal premiums thereon.809 The application must be filed with the auditor and state the following:
The auditor, upon receiving the application, must set a time and location for a hearing on the application and provide ten days’ notice of the hearing by publication in each affected county and notice by mail given to the engineer, the attorney for the petitioners, and the auditor of each affected county.811 The contractor is responsible for the costs of publishing the hearing notice.812
It is within the drainage authority’s discretion whether to reduce the contractor’s bond, but it must only do so after it determines that the contractor is not in default and that a loss will not result from reducing the bond.813 If the drainage authority orders the bond to be reduced, the bond amount must still be sufficient to protect the affected counties or watershed district from loss and damage and may not be reduced by more than 35 percent of the amount already paid to the contractor.814 The reduction does not affect the remaining amount on the bond, does not affect the liability incurred on the bond before the reduction, and does not affect a provision for a three-year guaranty of tile work.815
762 Minn. Stat. § 103E.501, subd. 1 (2015).
763 Minn. Stat. § 103E.501, subd. 3 (2015).
764 Minn. Stat. § 103E.501, subd. 4 (2015).
765 Minn. Stat. § 103E.501, subd. 3 (2015).
766 Minn. Stat. § 103E.501, subd. 3 (2015).
767 Minn. Stat. § 103E.501, subd. 3 (2015). The county auditor or watershed district secretary fixes the amount of liquidated damages owed for each day the contract fails to perform. Minn. Stat. § 103E.501, subd. 3 (2015). The function of liquidated damages is to provide the contractor with an incentive to finish the project in a timely manner. Beyond that, liquidated damages are required because it is difficult to prove the amount of damages incurred by the drainage authority when the project is completed late. Liquidated damages are often threatened, but seldom recovered. The problem with liquidated damages is the courts hold uniformly that liquidated damages may not be awarded unless there are some actual damages incurred by the person who has the right to claim liquidated damages. When a project is late in being completed, the persons who experience the loss are the affected landowners. It has been held that landowners have no right to recover from the contractor or from the contractor's performance bond for loss of profits arising from failure to complete a project on time. Grams v. Murphy, 103 Minn. 219, 114 N.W. 753 (Minn. 1908). Apparently, this is still good law since this case has never been overturned.
768 Minn. Stat. § 574.26, subd. 2 (2015).
769 Minn. Stat. § 574.26, subd. 2 (2015).
770 Minn. Stat. § 574.26, subd. 3 (2015).
771 Minn. Stat. § 574.26, subd. 3 (2015).
772 Minn. Stat. § 574.26, subd. 3 (2015).
773 Minn. Stat. § 574.26, subd. 2 (2015).
774 Minn. Stat. § 103E.501, subd. 5 (2015).
775 Minn. Stat. § 103E.501, subd. 4 (2015).
776 Minn. Stat. § 103E.501, subd. 4 (2015).
777 Minn. Stat. § 103E.501, subd. 4 (2015).
778 Minn. Stat. § 103E.501, subd. 6 (2015).
779 Minn. Stat. § 103E.501, subd. 6 (2015).
780 Minn. Stat. § 103E.501, subd. 6 (2015).
781 Minn. Stat. § 103E.501, subd. 6 (2015).
782 Minn. Stat. § 103E.501, subd. 2 (2015).
783 See Minn. Stat. § 103E.121 (granting the Director of the Division of Waters of the Department of Natural Resources the authority to investigate the methods used in the manufacture of drain tile, determine the causes of drain tile failure, and conduct research and experimentation to improve the quality of drain tile).
784 Minn. Stat. § 103E.551, subd. 1 (2015).
785 Minn. Stat. § 103E.551, subd. 1 (2015).
786 See Minn. Stat. § 103E.551, subd. 2 (2015).
787 Minn. Stat. § 103E.551, subd. 2 (2015).
788 Minn. Stat. § 103E.551, subd. 3 (2015).
789 Minn. Stat. § 103E.551, subd. 3 (2015).
790 Minn. Stat. § 103E.551, subd. 3 (2015).
791 Minn. Stat. §§ 103E.521 & 103E.531, subd. 1 (2015).
792 Minn. Stat. § 103E.531, subd. 1 (2015).
793 Minn. Stat. § 103E.531, subd. 2 (2015).
794 Minn. Stat. § 103E.531, subd. 2 (2015).
795 Minn. Stat. § 103E.531, subd. 2 (2015).
796 Minn. Stat. § 103E.531, subd. 2 (2015).
797 Minn. Stat. § 103E.531, subd. 2 (2015).
798 Minn. Stat. § 103E.531, subd. 3 (2015).
799 Minn. Stat. § 103E.531, subd. 3 (2015).
800 Minn. Stat. § 103E.535, subd. 1 (2015).
801 Minn. Stat. § 103E.535, subd. 2 (2015).
802 Minn. Stat. § 103E.535, subd. 3 (2015).
803 Minn. Stat. § 103E.541 (2015).
804 Minn. Stat. § 103E.541 (2015).
805 Minn. Stat. § 103E.541 (2015).
806 Minn. Stat. § 103E.541 (2015).
807 Minn. Stat. § 103E.541 (2015).
808 Minn. Stat. § 103E.541 (2015).
809 Minn. Stat. § 103E.545, subd. 1 (2015).
810 Minn. Stat. § 103E.545, subd. 1 (2015).
811 Minn. Stat. § 103E.545, subd. 2 (2015).
812 Minn. Stat. § 103E.545, subd. 2 (2015).
813 Minn. Stat. § 103E.545, subd. 3 (2015).
814 Minn. Stat. § 103E.545, subd. 3 (2015).
815 Minn. Stat. § 103E.545, subd. 3 (2015).
This page was last edited on 19 October 2016, at 17:35.
Template:Footer